Introduction
Force majeure clauses are a common feature of commercial contracts, They allocate risk for specified supervening events, such as war, natural disasters, pandemics, or governmental action, but their operation depends entirely on the wording adopted by the parties. In Singapore, the clause will be construed by reference to its terms, and mere increase in cost or reduced profitability will not ordinarily be enough unless the clause is drafted to cover that situation. By specifying in advance the events that qualify for relief, as well as the consequences that follow, these clauses enhance commercial certainty for contracting parties.
Ultimately, this article seeks to consider three key aspects of force majeure clauses: (a) their typical scope; (b) the steps involved for their invocation; (c) the legal consequences arising from their enforcement. It also seeks to describe the differences between force majeure clauses and the doctrine of frustration with which such clauses are loosely associated.
Executive Summary of Force Majeure Clauses
In general, a force majeure clause is a contractual provision that sets out how contracting parties will address specified events – such as war, natural disasters, or market disruptions –, which arise beyond the parties’ control, and render the performance of contractual obligations impossible.
To successfully invoke a force majeure clause, the relying party must bring itself squarely within the wording of the clause and satisfy any express procedural requirements. Depending on the drafting, this may require proof that a specified event occurred, that the event was beyond the party’s control or without its fault, and that the event prevented, hindered, or delayed performance to the extent contemplated by the clause. Once invoked, the clause may either suspend or discharge the affected party’s obligations (depending on its specific terms), and non-performance whilst the clause is operating will not constitute a breach of contract.
Let Us Help You Find Support
Tell us more about your situation at +65 8887 6076 to see how we may be able to help. There’s no cost to get started.
What are Typical Elements of Force Majeure Clauses?
Broadly, a typical force majeure clause comprises three key elements. First, it will identify certain supervening events (e.g., war, natural disasters (“acts of God”), market disruptions) for which the contracting parties intend to make special provision. Crucially, these events must be defined with sufficient specificity and clarity to properly reflect the parties’ intentions. This is because the courts have consistently adopted a narrow and strict approach when construing force majeure clauses. As a result, even where a clause appears, at first glance, to encompass a particular event, the court may nevertheless conclude that it falls outside the scope of the provision. If such indeed happens, however, the party may instead have recourse in frustration but that depends on whether the event radically changes the contractual obligation and is not otherwise allocated by the contract.
Second, a typical force majeure clause will set out the legal consequences which are to follow upon the occurrence of the supervening event(s). In doing so, the clause allows contracting parties to manage and allocate risk when these supervening events materialize to minimize loss. Ultimately, the precise consequences that will follow are highly dependent on the terms of the precise force majeure clause and the parties’ intentions. Most commonly, the contract will either be terminated, and the parties’ discharged from further performance; or the parties’ performance obligations will be temporarily suspended for the duration of the event, with the contract otherwise remaining in force.
Third, in some cases, force majeure clauses may operate to exclude or modify the application of the doctrine of frustration. Where such a clause purports to do so, it must be expressed in clear and unambiguous terms. The effect of such drafting is that the contract will continue to bind the parties even in circumstances which might otherwise have discharged them under the doctrine of frustration. Such “anti-frustration” clauses are recognized because the courts seek to give effect to the parties’ intention and uphold individuals’ freedom to contract on their own terms.
How Can Contractual Parties Rely on Force Majeure Clauses?
Where a party seeks to rely on a force majeure clause, the burden of proof rests squarely on that party. Two key elements must generally be proven:
First, the party must show that an event falling within the scope of the clause has in fact occurred. This typically involves both a matter of contractual interpretation, demonstrating that the alleged event falls within the wording of the clause; as well as an evidential inquiry into whether the alleged event indeed materialized.
Second, the party must show that the event falls within the clause and satisfies any additional requirement in the clause, such as a “beyond control” or “without fault” criterion. Whether the party must also take all reasonable steps to avoid or mitigate the event depends on the wording of the clause and it is not a universal rule. If the event, or its effects, could reasonably have been avoided or overcome, it may be characterized as self-induced, in which case the party would not be permitted to rely on the clause to escape liability. Finally, it bears mention that mere difficulty in performance or an increase in the cost of performance will not suffice. Rather, the party must show that the supervening event has, in substance, rendered performance impossible or radically different from that which was originally contemplated under the contract.
How are Force Majeure Clauses Applied in Real-life Situations?
RDC Concrete Pte Ltd v Sato Kogyo (S) Pte Ltd and another appeal [2007] 4 SLR(R) 413 5
The parties contracted for the purchase of ready-mixed concrete. The court had to consider whether (a) shortages of raw material (aggregates and cement), and (b) plant breakdowns were events that fell within the force majeure clause which provided as follows:
In the event of any circumstance constituting Force Majeure, which is defined as act of God, or due to any cause beyond the supplier’s control, such as market raw material shortages, unforeseen plant breakdowns or labour disputes, the duty of the affected party to perform its obligations shall be suspended or limited until such circumstance ceases.
Ultimately, as regards (a), the court held that because there was insufficient evidence of cement shortage, it was unclear whether there was an event which fell within the force majeure clause. In any event, the court noted that it was still within Sato’s power to purchase aggregates from the market, albeit at a higher price. The requirement of impossibility to invoke the force majeure clause was therefore not satisfied on the facts. Meanwhile, as regards (b), the court held that even though the breakdown of the plant used was independent of Sato’s fault, Sato could have applied for the Land Transport Authority’s permission to use other concrete plants and mitigated the consequences of the breakdown. Their failure to do so therefore did not entitle them relief under the force majeure clause. In other words, the clause did not assist the defendant on the facts because the wording of the clause, the evidence, and the available alternatives did not support relief.
Glahe International Expo AG v ACS Computer Pte Ltd [1999] 1 SLR(R) 945
The parties contracted for the sale and delivery of computers to Moscow. The court had to consider whether the imposition of customs duty and/or the inflation in Russia were events that fell within the force majeure clause which provided as follows:
Neither Party shall be responsible for the complete or partial non-performance of any of its obligations, if the non-performance results from such circumstances as flood, fire, earthquake, and other Acts of God, as well as war, military operations, blockade, act or actions of state authorities, or any other circumstances beyond the Parties’ control that have arisen after the conclusion of the Contract (except for failure to pay any sum which has become due under the provisions hereof).
Ultimately, the court held that the imposition of a mere 15% tax was not so huge or astronomical as to constitute an event of force majeure. This is because performance of the contract was still possible, albeit more expensive and costly. Hence, Glahe was obligated to fulfil its contractual obligations. The case is authority for the proposition that a mere increase in cost or burden is ordinarily insufficient. The event must fall within the clause, or, in the case of frustration, must radically alter the parties’ obligations.
What Should Parties Take Note of When Drafting Force Majeure Clauses?
1. Contracting parties should ensure that any events which may render contractual performance more difficult or impossible are expressly and unequivocally provided for in the force majeure clause. Clear and specific drafting reduces uncertainty and minimizes the risk of the clause being narrowly construed or found inapplicable.
2. Before suspending or halting performance on the basis of a force majeure event, it would be prudent for a party to seek legal advice and confirm that the requirements of the clause are in fact satisfied. This includes ensuring that the alleged event falls within the scope of the clause and that any procedural obligations (such as notice requirements, time limits, or obligations to provide supporting evidence) are strictly complied with. Failure to adhere to these requirements may itself constitute a breach of contract and expose parties to unwanted liability.
3. Further, and in connection with (2), parties should take all reasonable steps to mitigate the effects of the force majeure event. This may include exploring alternative means of performance, reallocating resources and manpower, or otherwise taking proactive measures to minimize disruption. A failure to do so may disallow parties from relying on the clause and create unwanted liability.
What Happens Once Force Majeure Clauses are Invoked?
Once the clause is validly invoked, the consequences stipulated in the contract will take effect. Depending on the terms, this may result in the suspension or discharge of contractual obligations, and the affected party will not be liable for non-performance or breach. Comparatively, if the clause cannot be validly invoked, the innocent party may seek compensation for breach of contract in the usual manner under the law.
What is the Difference Between Force Majeure and Frustration?
Although both force majeure clauses and the doctrine of frustration operate, in a broad sense, as mechanisms that excuse or limit contractual liability in the face of supervening events beyond the control of the contracting parties, they are conceptually distinct and it is important not to conflate the two. Three main differences may be identified:
First, a force majeure clause is a creature of contract, allocating responsibility in advance for foreseeable specified events that contracting parties have identified as potentially disruptive. By contrast, the doctrine of frustration is a common law doctrine which applies only where an unforeseen supervening event occurs, such that performance becomes impossible or radically different from what was contemplated.
Second, force majeure clauses, allow contracting parties to define, through careful drafting, the precise scope of triggering events and the consequences that ought to follow. They hence allow for better risk allocation between the parties and have been characterized as more “certain” than the doctrine of frustration. Another facet of uncertainty attributable to the doctrine of frustration is the difficulty of invoking it.
Finally, the legal consequences of each differ significantly. Under a force majeure clause, parties are free, per the principle of freedom to contract, to determine the consequences that follow upon the occurrence of a specified event. By contrast, where frustration arises, the parties are automatically discharged, by operation of law, from their contractual obligations. The precise relief receivable by the parties is governed by the Frustrated Contracts Act 1959 (2020 Rev Ed), which sets out the statutory consequences that follow once frustration is established.
Conclusion
In conclusion, force majeure clauses play an important role in commercial contracting as a proactive mechanism for allocating risk in the face of supervening events that may disrupt performance. By allowing parties to define in advance both the scope of triggering events and the legal consequences that follow, such clauses promote contractual certainty and reflect the underlying principle of freedom of contract. However, their effectiveness ultimately depends on careful drafting and strict compliance with their terms, including any procedural and evidential requirements for invocation.
Disclaimer
This article is intended for general informational purposes only and does not constitute legal advice. While every effort has been made to ensure the accuracy and relevance of the information provided, readers are encouraged to consult a qualified legal professional for advice tailored to their specific circumstances. The content reflects the legal position in Singapore as of the time of writing and may be subject to changes in legislation or legal interpretation.